HIGHLAND HORIZON POOL closed for REPLASTERING
Project Details
Location: Highland Horizon Pool, 416 Highland Horizon, Austin, TX 78717
Description: In order to keep District facilities properly maintained, the Brushy Creek MUD Board of Directors has approved the replastering of the Highland Horizon Pool.
Impact to the Community during Construction: The pool will be closed from February 1 to March 15, 2021. A small section of the parking lot will be occupied by construction vehicles. There may be plaster dust emitted in the air and mechanical noise during construction.
Contractor: Lifeguard4Hire
Project Timeline: The project will begin on February 1, 2021 and the estimated completion date is March 15, 2021. The pool will be closed for the duration of the project.